- Pre-engineered metal building (PEMB) designed to provide additional area needed by the company to allow for increased productivity, efficiency of production and modernization of equipment
- Design-build project was a 10-month effort from design commencement to project closeout
- Followed the Plant 1 expansion and expands on the company’s desires for increased productivity and efficiency in delivering products to their clients
- Includes office space, mezzanine, restroom and break areas, as well as paint booths, testing and balancing equipment, vehicle-fluids storage, other process equipment and pits